Summary
In December 1992, Beaver Island Community School presented building-project plans, prepared bid materials, hired a project supervisor, and described a phased construction and remodeling schedule.
Evidence limits
The article records a bid process and target schedule, not an awarded general contract, completed construction, or final inspection.
Sources
- Reports seven bids above the $750,000 estimate, February resident meetings, project priorities and reductions under consideration, and the February 18 decision to hire Hallmark Construction for $815,420 with many Island subcontractors. The holding institution's portal restricts automated access; the archive holds a copy of this issue and can provide it on request.data1 · beaver-island-archive · beaver_beacon · 1993-02_Beaver-Beacon
- The held twelve-page issue scan confirms the school-project award and redesign report.data1 · beaver-island-archive · scans · beaver_beacon · issues · 1993-02_Beaver-Beacon
- Reports that twelve general contractors had picked up specifications and bid drawings by January 4, including contractors with Island ties, with proposals due February 4. The holding institution's portal restricts automated access; the archive holds a copy of this issue and can provide it on request.data1 · beaver-island-archive · beaver_beacon · 1993-01_Beaver-Beacon
- The held twelve-page issue scan confirms the school-project procurement report.data1 · beaver-island-archive · scans · beaver_beacon · issues · 1993-01_Beaver-Beacon
- Reports the architect’s presentation, bid-drawing availability, preference for bidders using Island subcontractors, Joddy Croswhite’s project-supervisor role, phased gym/library/computer/science-lab work, and a September 1, 1993 completion target. The holding institution's portal restricts automated access; the archive holds a copy of this issue and can provide it on request.data1 · beaver-island-archive · beaver_beacon · 1992-12_Beaver-Beacon
- The held twelve-page issue scan confirms the school-building project report.data1 · beaver-island-archive · scans · beaver_beacon · issues · 1992-12_Beaver-Beacon
Added 4 August 2026. Recent changes
Cite this article
Beaver Island Archive, “Beaver Island Community School advances its building-project bid process, 1992”, https://beaverislandarchive.org/events/beaver-island-school-building-project-bids-1992/, accessed [date], citing Beaver Beacon, February 1993, “BUILDING PROJECT CHALLENGES SCHOOL BOARD.” (and 5 further sources listed on the page).
Last revised 2026-08-04. Fill in [date] with the date you read it — this page is static and cannot know that.
BibTeX for “Beaver Island Community School advances its building-project bid process, 1992”RIS for “Beaver Island Community School advances its building-project bid process, 1992”