Beaver Island ArchiveA primary-source archive & encyclopedia45°40′N 85°33′W · Lake Michigan
Colour scheme
Search

Event

Little Traverse Conservancy and island volunteers build a new Barney's Lake trail

Also Barney's Lake Preserve Scully Addition trail 2013

Draft — sources verified, prose evolving

Locator map: Beaver Island highlighted within the Beaver Island archipelago
Took place at Beaver IslandLocator plate © OpenStreetMap contributors (ODbL 1.0); depths NOAA; names USGS GNIS. How the plates are drawn.
TypeEvent
Dates2013-09-23 – 2013-09-24
WithinBeaver Island
ErasModern era
On this page
Locator map: Beaver Island highlighted within the Beaver Island archipelago
Took place at Beaver IslandLocator plate © OpenStreetMap contributors (ODbL 1.0); depths NOAA; names USGS GNIS. How the plates are drawn.
Event
Dates
2013-09-23 – 2013-09-24
Kind
Construction
Where
Beaver Island
Carried out by
organization/little-traverse-conservancy
Eras
Modern era
Concepts
conservationrecreationinfrastructuretourism
Within
Beaver Island

Summary

On September 23–24, 2013, Little Traverse Conservancy staff and ten island volunteers constructed a three-quarter-mile trail linking Barney’s Lake Road with the Kuebler Trail through the Scully Addition to Barney’s Lake Preserve. The work also added a naturally surfaced four-car parking area, trail maps, bench-cut sections, and blue blazes. The issue describes the preserve as 285 acres after the addition.

Evidence limits

The source documents the completed trail segment and associated improvements. It describes possible future trail segments as proposals, not completed work.

Open questions

  • Were the additional trail segments described as proposals in the October 2013 account ever built?
  • The preserve is described here as 285 acres after the Scully Addition — does this match the Conservancy’s current published acreage for Barney’s Lake Preserve?

If you can answer any of these, or correct anything above, the archive wants to hear it — see Corrections.

Sources

  1. Beaver Beacon, October 2013, "New Trail at Barney's Lake."
    Reports that Little Traverse Conservancy staff and ten island volunteers built a three-quarter-mile trail linking Barney's Lake Road with the Kuebler Trail through the Scully Addition, with parking, maps, bench-cut sections, and blue trail blazes. No public copy of this file is known; the archive holds one and can provide it on request.
    data1 · beaver-island-archive · beaver_beacon · 2013-10_Beaver-Beacon
  2. The held October issue scan confirms the trail-construction report.
    data1 · beaver-island-archive · scans · beaver_beacon · issues · 2013-10_Beaver-Beacon

Added 6 August 2026. Recent changes

Cite this article

Beaver Island Archive, “Little Traverse Conservancy and island volunteers build a new Barney's Lake trail”, https://beaverislandarchive.org/events/beaver-island-barneys-lake-scully-addition-trail-2013/, accessed [date], citing Beaver Beacon, October 2013, "New Trail at Barney's Lake." (and 1 further source listed on the page).

Last revised 2026-08-06. Fill in [date] with the date you read it — this page is static and cannot know that.