- Dates
- 1999-11 – 2000-01
- Kind
- Construction
- Where
- Beaver Island
- Eras
- Modern era
- Concepts
- heritagearchitecturerecreationartscommunitycommunication
- Within
- Beaver Island
Summary
PABI reported that final drawings for Phase I of the Beaver Island Community House were complete in November 1999 and that a silent capital campaign was underway. The update also records PABI’s participation with both townships and Beaver Island Community School in the Youth Consortium, which sponsored Youth Activities Director Elaine West and a program spanning recreation, arts, and a school yearbook.
Evidence limits
The notice reports project readiness and organizational participation; it does not establish that construction or the capital campaign was completed.
Sources
- Reports final drawings for Phase I, a silent capital campaign, the office move to the Bank Building, and participation with both townships and the Community School in funding and sponsoring Youth Activities Director Elaine West. The holding institution's portal restricts automated access; the archive holds a copy of this issue and can provide it on request.data1 · beaver-island-archive · beaver_beacon · 1999-11_Beaver-Beacon
- The held issue scan confirms the Community House update.data1 · beaver-island-archive · scans · beaver_beacon · issues · 1999-11_Beaver-Beacon
- Reports final Phase I drawings, the $1,979,900 Phase I capital-campaign budget, three naming opportunities already taken, and the decision to defer Phase II spending until Phase I is fully funded. The holding institution's portal restricts automated access; the archive holds a copy of this issue and can provide it on request.data1 · beaver-island-archive · beaver_beacon · 2000-01_Beaver-Beacon
- The held issue scan confirms the Community House update.data1 · beaver-island-archive · scans · beaver_beacon · issues · 2000-01_Beaver-Beacon
Added 5 August 2026. Recent changes
Cite this article
Beaver Island Archive, “PABI receives final Phase I drawings and joins the Beaver Island Youth Consortium in November 1999”, https://beaverislandarchive.org/events/beaver-island-community-house-phase-i-final-drawings-1999/, accessed [date], citing Beaver Beacon, November 1999, “Community House Update.” (and 3 further sources listed on the page).
Last revised 2026-08-05. Fill in [date] with the date you read it — this page is static and cannot know that.
BibTeX for “PABI receives final Phase I drawings and joins the Beaver Island Youth Consortium in November 1999”RIS for “PABI receives final Phase I drawings and joins the Beaver Island Youth Consortium in November 1999”